- The project was complicated from concept to delivery, as many of the modules were dimensionally different, had varied floor loadings and required manufacture and delivery in a precise order.
- Over 700 tonnes of parts were processed and delivered in a 4 week window in accordance with EXC 2 to EN1090-1
- Approximately 400 tonnes was Laser cut, Laser cut and tapped, or sawn to length and supplied from Leeds
- The balance was 380mm & 430mm wide PFC which was saw cut, drilled, tapped on the saw & drill line in Dundee and subsequently delivered direct.
The accuracy of the products supplied and the co-ordinated scheduling of deliveries resulted in the desired build time being achieved, whilst also reducing time through the factory by over 50%.